New Build Construction
Swale River Crossing, Kent, England

column access on Swale River crossing.
Two 7.5m long mast climbing work platforms were used on each reinforced column for safe and efficient access during the construction process. The crossing superstructure is supported by a series of 18 pier bases, each pier base comprising of two tapering reinforced concrete columns to a maximum height of 30 metres. Five pier bases were within
the tidal river estuary with the remaining thirteen pier bases on land.
The challenge was for the provision of a safe and efficient access to the concrete columns during construction. Each pair of columns were different in height and tapered from a maximum diameter of 3.85 metres at the base to a uniform 3 metres at the top. A unique solution was engineered using mast-climbing work platforms supplied by Alimak Hek Ltd, the country’s leading authority on vertical access methods.
Due to the tapering of the columns, Alimak Hek technical engineers utilised two inclined and independently operated mast climbing work platforms on each column. Each platform had a specially profiled 7.5 metre long deck which was fully adjustable to meet the tapering column dimensions and to ensure total encapsulation at all times. The two platforms then provided a flexible and unobstructed access solution to all areas of the pier columns.
The first work platforms were installed in August 2004 with the final pier completed in May 2005. The use of eight Alimak Hek customized work platforms working in pairs allowed for optimum speed throught out the construction programme including the positioning of the prefabricated steel reinforcing cages, the erection of the steel shuttering, the pouring of the concrete and the striking of the steel formwork shuttering. A travel speed of 10 metres per minute and a distributed payload capacity of 1,200 kg allowed the easy transportation of personnel and materials to the required working height. Onboard power outlets on the platforms made it possible to use power tools as conveniently as if in the workshop.
The platforms provided a rigid working area from which to construct all the column piers and worked with few problems during the contract period. The main contractors major problem was the high wind speeds, which restricted working at certain times.
Downloads
Image From The Swale River Crossing (1)
Image From The Swale River Crossing (2)
Image From The Swale River Crossing (3)
Image From The Swale River Crossing (4)
Swale River Crossing reference sheet







